Connect to Project Activity
Explanation
This activity is used to manually connect a material requisition line to a project activity when issuing part, from the material requisition line itself. This activity is performed to obtain the cost of the project activity of goods being requested for the project through the material requisition.
Prerequisites
- For user's default site the inventory part must have been entered
- The project to be connected must be in the Approved or Started status.
- The project activity must be in the Released status to be available.
- The site of the material requisition line must be defined as an allowed site for the connected project.
- The relevant posting type must have been specified for the project code part.
- The project code part must not have been pre-posted with a financial project.
- Project manual connections to the material requisition lines must have been made available on the Project /Manual Connections tab.
System Effects
Project is connected to the material requisition.